A cloud migration preparation checklist for IT leaders

The operational prep before a migration starts: application inventory, the pre-flight checklist, and the infrastructure plan you need signed off.

6 min read Updated 28 September 2026
A cloud migration preparation checklist for IT leaders

This is the preparation work, in the order an IT leader has to do it, with the artefacts each step has to produce.

It assumes the decision to migrate is already made. If you are still deciding, Switzerland’s cloud moment: is your business ready? is the readiness assessment; this is what happens once the answer is yes.

Step 1 — Write down the objective, with a number

Before any inventory work, one sentence with a measurable outcome and a date. Not “migrate to the cloud” — something that can be true or false at a point in time.

Three shapes that work:

  • “Reduce fully-loaded infrastructure cost per environment by X% by Q3”
  • “Cut provisioning time for a new test environment from three days to under two hours by Q2”
  • “Move to a documented recovery time of under four hours for the three business-critical systems by year end”

The artefact: one sentence, agreed with the business sponsor, that every later trade-off is decided against.

Step 2 — Inventory and categorise applications

The single most laborious step and the one everything else depends on. The unit is the application or workload, not the server.

Per application, capture:

FieldWhy it matters
Business ownerSomeone has to decide and sign off
Users and volumeDistinguishes critical from forgotten
Load profile across a yearDetermines sizing and whether elasticity helps
Data classificationSets the regulatory constraint
Dependencies, both directionsDetermines what moves together
Cost of an hour downSets the wave it belongs in
Fully-loaded current costThe baseline every later claim needs

Then categorise. The standard six — retire, retain, rehost, replatform, refactor, replace — with a named reason each.

Two findings this step reliably produces. First, several applications have no users at all; retiring them is the cheapest win available. Second, the dependency map is wrong, because some connections were never documented. Better to learn that now than during a cutover.

The artefact: a spreadsheet with one row per application, a disposition, and a named owner. Nothing proceeds without it.

Step 3 — Settle the regulatory questions

These constrain architecture, so they come before design, not after.

  • Data residency per class. Which data must stay in Switzerland, which may sit in the EU, which is unconstrained. Most estates have less constrained data than the blanket assumption suggests.
  • Access control. Who can reach the data — including provider support staff in other jurisdictions, and sub-processors behind them. This is the question that gets audited under revDSG/nDSG and GDPR; storage location is not.
  • Retention. Minimums and maximums per data class, and how the new environment will enforce them.
  • Exit. For FINMA-supervised businesses a documented, demonstrable exit is a requirement. For everyone else it is the difference between a supplier and a dependency.

The artefact: written answers, reviewable by whoever signs off compliance. If these live only in someone’s head, they do not exist.

Step 4 — The pre-flight checklist

Per wave, before anything moves:

  • Baseline metrics captured — performance, cost, availability
  • Rollback plan written and executed at least once
  • Backups verified by restoring, not by checking a green tick
  • Owner identified for each application in the wave
  • Cutover window agreed with the business, including who decides to abort
  • Communication plan — who is told what, and when
  • Success criteria defined before the move, not chosen afterwards

The rollback line is the one most often assumed rather than done. A rollback plan that has never been executed is a hypothesis, and the first time you find out is the worst time.

Step 5 — The infrastructure plan

What the landing zone contains, agreed and signed off before the first workload arrives:

Network and identity — segmentation, how access is granted, how it is reviewed, and by whom.

Observability — what is logged, retained how long, who reads it, and what triggers an alert. Do not economise here; it is the evidence you need during an incident and, for regulated workloads, part of what you are obliged to keep.

Backup and recovery — recovery point and recovery time objectives per application class, taken from the business rather than from IT, and tested.

Cost attribution — tagging by team or product from day one. Retro-fitting tags across a live estate is genuinely miserable work.

Guardrails — budget alerts, mandatory tags, default size limits. Guardrails scale; approval steps get routed around.

The artefact: a written landing-zone definition, reviewed by someone who did not write it.

Step 6 — Name the owners

Three roles, with actual names attached, before the first wave:

  • Migration lead — decides sequence and go/no-go per wave
  • Cost owner — reports variance monthly, from day one rather than after go-live
  • Platform owner — owns the landing zone after the programme ends

The third is the one that gets forgotten, and its absence is why estates freeze in their migration-day shape. The optimisation that produces the savings happens after the programme, or it does not happen.

What “prepared” looks like

Six artefacts. If you have all six, the migration is a scheduling exercise. If you are missing two or more, the migration will discover them for you at a worse moment.

  1. An objective, one sentence, with a number and a date
  2. An application inventory with dispositions and owners
  3. Written regulatory answers on residency, access, retention and exit
  4. A pre-flight checklist per wave, with a tested rollback
  5. A signed-off landing-zone definition
  6. Three named owners

If you want these six artefacts produced for your estate, book a call. No obligation.

Cloud Migration Checklist Application Inventory Planning IT Leadership